Port aux Basques Harbour Navigation Improvement
Marine Atlantic is planning navigation improvements within Port aux Basques Harbour. This project is intended to improve marine navigation efficiency and safety, while supporting ongoing ferry operations.
We invite members of the public, Indigenous groups, stakeholders, and interested parties to attend a public open house to learn more about the proposed project.
Date: September 1, 2026
Times: Afternoon session 2pm - 4pm | Evening session 6pm - 8pm
Location: St. Christopher's Hotel, Channel-Port aux Basques
About the open house
This open house will provide an opportunity to:
- Learn about the project purpose and proposed works
- Review environmental considerations and mitigation measures
- Speak directly with members of the project team
- Provide comments and ask questions
Project information materials will be available, and all feedback received will be considered as the project advances through design and environmental review processes.
Accessibility
Accommodation requests can be made in advance to support your participation.
Unable to attend?
If you are unable to attend the open house but would like to receive information or provide input, please fill out the below form:
Frequently Asked Questions
Why is this project needed?
Why is this project needed?
Port aux Basques Harbour currently has navigation constraints, particularly Vardy’s Rock, that make it difficult for ferries to safely maneuver, especially in poor weather. This project will improve the entrance channel and establish a new turning basin to provide better maneuverability for our vessels, and will improve safety, reliability, and operational efficiency.
What is the timeline for the project?
What is the timeline for the project?
We are currently in the design stage of the project. Our goal is to gather the necessary information to obtain regulatory permits and approvals over the next several months. We will complete a joint environmental evaluation to satisfy requirements of both the Province of Newfoundland and Labrador’s Department of Environment, Conservation and Climate Change (ECC) environmental registration process and the federal Impact Assessment Act (IAA) process. We are seeking to obtain the required regulatory permits/approvals from the provincial and federal departments. Our goal is to complete the regulatory review process over the next several months.
What approvals are needed?
What approvals are needed?
- Environmental assessment registration by the province
- Assessment of impacts by the federal departments
- Authorization from DFO under the Fisheries Act
- Approval from Transport Canada under the Canadian Navigable Waters Act
- Approval from the province to alter a waterbody
- Environment and Climate Change Canada (ECCC) are also involved in the review of impacts.
How long will construction take?
How long will construction take?
Construction is expected to take approximately 12 months once approvals are in place.
How will you remove the island?
How will you remove the island?
We are in the design stage of the project therefore no final decision has been made on how the removal will occur. Because the material requiring removal is essentially rock, we do know it will involve managed blasting activities under the guidance of environmental and regulatory authorities.
What are the key environmental concerns?
What are the key environmental concerns?
Key concerns include:
- Noise (especially blasting)
- Effects on fish and fish habitat
- Temporary impacts on fisheries
- Marine mammal disturbance
What mitigation measures are being proposed?
What mitigation measures are being proposed?
Mitigation includes:
- Daytime blasting
- Environmental monitoring (noise, water quality)
- Marine mammal observation and shutdown zones
- Sediment control
- Habitat offsetting
Will monitoring be required?
Will monitoring be required?
Yes. Monitoring programs will be implemented during and after construction to confirm mitigation effectiveness and regulatory compliance.
What fisheries will be impacted?
What fisheries will be impacted?
It is recognized that the lobster fishery could be impacted while the project is ongoing. Part of our current project planning is to establish ways to mitigate potential impact during construction. Once the project is completed and the habitat is replaced it is anticipated that the lobsters will return; post construction monitoring will be conducted to confirm this.
Lobster is a key concern identified by local fishers. There may be temporary disruption during construction, but the project includes habitat creation and enhancement measures that may benefit lobster populations over the long term.
Marine Atlantic respectfully acknowledges that we operate in Mi’kma’ki, the ancestral and unceded territory of the Mi’kmaq Peoples, and on the island of Ktaqmkuk, the unceded, traditional territory of the Beothuk and the Mi’kmaq Peoples. We also acknowledge Labrador as the traditional and ancestral homelands of the Innu of Nitassinan, the Inuit of Nunatsiavut, and the Inuit of NunatuKavut.